Finland’s Pöyry has been awarded implementation engineering services contracts by Stora Enso Oyj for CHP projects in Belgium and Germany.
Stora Enso is improving energy efficiency through investments totalling €260 million at the Langerbrugge mill in Belgium and the Maxau mill in Germany.
At both mills a new multifuel circulating fluidised bed boiler, a steam turbine, new fuel handling systems and auxiliary systems will be installed.
The aim of the investments is to enable CHP generation with a competitive fuel mix. Both projects are scheduled to be completed in 2010.
Pöyry’s contracts, valued at more than €3 million, cover implementation engineering services for the new power plants.