The commercial startup of Wisconsin Energy’s 615 MW Oak Creek Unit 2 expansion has been delayed due to problems with one of two main boiler feed pumps.

The 615 MWà‚ coal-fired generating unit completed critical performance tests necessary for the unit to be placed into commercial operation, the utility said in a filing with the Securities and Exchange Commission. One of these tests is an operability test, which requires the unit to achieve a minimum availability of 90 percentà‚ over a continuous 15-day period. The utility also said Unit 2 had completed the required net capacity and heat rate tests, as well as certain environmental tests.

The filing said one of the boiler feed pumps has had high vibration and also experienced sub-synchronous vibration, which it said occurs when the frequency of the vibration is different than the rotational speed of the pump.à‚ The utility said itsà‚ contractor, Bechtel Power Corp., is working with the pump manufacturer andà‚ also engaged a third party expert to review and correct these issues.à‚ 

The boiler feed pumps supply high temperature, high pressure water to the boiler, which turns this water into steam to power the unit’s turbine generator. Because of the issues with the boiler feed pump, Unit 2à‚ was not be placed into commercial operation and turned over toà‚ the utilityà‚ during the fourth quarter of 2010 asà‚ had been expected. The utility saidà‚ based on the schedule and information provided by Bechtel, Unit 2 couldà‚ be placed into commercial operation by Jan. 28.

The utility said in its filing ità‚ expects to collect liquidated damages under the contract with Bechtel. It cautioned the final amountà‚ may be adjusted asà‚ Bechtel likely will be entitled to schedule relief for the delay.

Read more news and features on power plant operations and maintenance.