HomeCoal FiredBrazil's Parnaàƒ­ba I's third turbine synchronized

Brazil’s Parnaàƒ­ba I’s third turbine synchronized

MPX of Brazil confirms that it has synchronized the third turbine at its Parnaàƒ­ba I thermoelectric plant to the national grid.

The power company said in a statement that the 169 MW turbine had been successfully operating in test mode since last Friday (22 March)

According to BNamericas, the Parnaàƒ­ba project’s final installed capacity will be 676 MW, when the fourth turbine comes on line later this year.

The facility will provide an average of 225 MW based on contracts secured during the A-5 auction held in2008, confirms MPX.


MPX owns 70 per cent of Parnaàƒ­ba I, with the remaining held by Petra Energia.

Parnaàƒ­ba I is part of the bigger 3.72 GW Parnaàƒ­ba thermoelectric complex, located in Maranhao state in the northeast.

For more Coal-Fired Power news.

For more Latin America news.

LATEST FEATURE