Concerns expressed over $316m Fukushima ice wall

A top nuclear power official has expressed concerns about Tokyo Electric Power Company’s Fukushima ice wall project.

Dale Klein, former head of the US Nuclear Regulatory Commission and a senior adviser to Tepco, told Kyodo News in Japan: "I'm not convinced the freeze wall is the best option. What I'm concerned about is unintended consequences. Where does that water go and what are the consequences of that? I think they need more testing and more analysis."
Fukushima workers
The $316m, 1500-metre wall is intended to contain irradiated water and keep Fukushima safe from the damaged nuclear reactors. It is intended to stay in use until 2020, using enough electricity every year to power 13,000 households, according to officials.

By next March Fukushima Daiichi's four damaged reactors will be surrounded by an underground frozen wall that will be a barrier between highly toxic water used to cool melted fuel inside reactor basements and clean groundwater flowing in from surrounding hills.

UK newspaper The Guardian reports that up to 400 tonnes of groundwater that flows into the basements each day must be pumped out, stored and treated – and on-site storage is edging closer to capacity. Decommissioning the plant will be impossible until Tepco addresses the water crisis.

The wall is being built with technology that has never been used on such a large scale. Tepco has also had problems freezing irradiated water – using the same method being used to build the underground wall – that has accumulated in underground trenches, raising concerns that the ice technology is flawed.

The company had safely removed 1200 of the 1500 nuclear fuel assemblies that were being stored in a pool in Reactor 4 when the tsunami smashed into the plant, knocking out backup power supplies and sending three of its reactors into meltdown.

Attempts to address the buildup of contaminated water in reactor basements suffered a serious setback last year when storage tanks sprung leaks. Meanwhile, the plant's water treatment facility, which can remove all radioactive nuclides except tritium, has been suspended several times owing to malfunctions.

For more nuclear power news

Follow Power Engineering International on Twitter

Related Articles

Teyssen determined to complete E.ON power plant spin off

E.ON's Chief Executive Johannes Teyssen says he is pursuing the spin off of the company’s power plants regardless of cost.

EDF-Areva to take on the cost of Hinkley Point C nuclear over runs

EDF-Areva has confirmed that it will bear the cost of any over runs associated with the Hinkley Point C nuclear power project.

Latest Articles

Editor's Picks

GE unveils transformational Digital Power Plant

GE yesterday unveiled a digital initiative that it claims will revolutionise the power industry and save plant operators b...
Anne Carpenter of IEA Clean Coal Centre

Report highlights need for enlightened approach to water and power generation

The International Energy Agency’s Clean Coal Centre has produced its latest insights into what is referred to as the ‘wate...

UK gives £2bn backing to Hinkley Point nuclear project

The UK government has reaffirmed its commitment to Hinkley Point C new nuclear power station by unveiling a £2bn ($3.1bn) ...

Policy tinkering sees financial lure of UK renewables sector plummet

The UK’s attractiveness for renewables investment has plummeted in the last few months thanks to “policy-making in a vacuu...

US leapfrogs China to top renewables investment table

The US has leapfrogged China to the top slot in a highly-regarded annual analysis of the best countries in the world for r...

Editorial Guides

Lubrication Challenges for the Biogas Industry in 2015

The biogas industry is growing in importance as the world continues to look for alternative, clean energy sources. However...

Maximising Power Plant Efficiency

The need for power plants to operate at maximum efficiency and flexibility while cutting emissions is greater than ever be...

How to cut your OPEX

How to cut your OPEX In a constantly evolving electricity market, factors such as over capacity and low coal costs can pu...

Buyers Guide Companies

Rolls Royce Energy Systems

We supply gas turbines, compressors and diesel power units to customers ...

Lenox Instrument Co

Lenox Instrument Co is a manufacturer of highly reliable fixed and porta...

ATG Electronics

For more than a decade, ATG Electronics has established itself as a lead...

SWAN Analytical Instruments AG

Is one of the leading manufacturers of online analytical instruments.

Bran & Luebbe, An SPX Brand

Bran & Luebbe, an SPX brand, has been a worldwide leader in metering, an...

Buyers Guide Products


Compact voltage regulator, integrates all ...

Excitation System

Our excitation systems are recognized worl...

DMT340 Series Dewpoint and Temperature Transmitters for Very Dry Conditions

The Vaisala DRYCAP® Dewpoint and Temperatu...

MHT410 Moisture, Hydrogen and Temperature Transmitter

The Vaisala Moisture, Hydrogen and Tempera...

Control Servo Motor SMR

A Voith control servo motor is a linear el...

Power Engineering International


The Effect of Moisture Sensor Location on Reliable Transformer Oil Monitoring

Power transformers are among the most valuable and important assets in electrical power networks and moisture is one of the key factors impacting the operational performance of transformer oil.&nbs...

Engineering & Design for Lean Construction

AVEVA introduces the benefits of Engineering and Design for Lean Construction by challenging the concept of ‘right first time design' and presenting a ‘Lean’ approach. A Lean approach to project ex...

Bridging the Power Gap in Africa: Testing options to manage constrained short to medium term system operations

Around the world, existing power systems face increasingly constrained operations in the short to medium term with available ageing generation capacity.  In this paper, PLEXOS® has been used t...

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New challenges and opportunities are continually appearing thanks to dramatic developments in technology...

Latest Digital Edition

Look Inside >
Current Issue

Article Archives for Power Engineering International Magazine