Energy body warning on unviable German power plants

The German energy industry association, BDEW, says that 43 per cent or 32 of the power plants planned for construction in Germany may never come to fruition, due to lack of economic viability.

The association’s managing director, Hildegar Mueller (pictured) said: "Unless there is clarity very soon about the future structure of the market and a relevant capacity market model, the situation for power stations will result in a serious problem for Germany as an industrial location."
Hildegar Mueller
The association says a combination of a lack of clarity about the future structure of energy markets and the lack of profitability for coal- and gas-fired power stations because of competing energy supplies from subsidised renewable power had severely undermined investor confidence.

BDEW said that a year ago, it had only questioned the economic viability of 22 long-term projects and warned that the situation had regressed to the point that unless action was taken to encourage the construction of more power stations to ensure stable supply, energy security issues were inevitable.

The report from BDEW was issued on the first day of the Hanover Trade Fair, when the body traditionally prescribes its solutions for a more effective German energy policy.

It warned that if current plant closure plans were added up with cancellations of new construction, some 13,600 MW of so-called secure load, that runs 24 hours, would be shut by 2022.

Reuters reports that wind and solar energy have been expanding fast but are not secure as they cannot guarantee supply at all times.

It said that on the positive side, nine offshore wind parks were due to come online this year and that the current rate of project completions was still high: five coal-fired and four gas-fired plants would come onstream in 2014 and 2015.

"This must not hide the fact that planning for these units began in the last decade and economic operations of these plants in today's market are in question," Mueller said.

Meanwhile, the head of Germany's main engineering body has warned that caution was required so as not to jeopardise German business interests in Russia.

"It is absolutely clear that there has been a blatant breach of international law. It is also clear that it is necessary to draw the line," VDMA President Reinhold Festge said at the same trade fair. "But you have to know what you are doing when you continue to escalate, yelling and screaming," he added.

"This concerns the engineering sector's fourth-biggest market, and there is no other country that has invested in Russia as massively as Germany," Festge said.

For more European power generation news

Follow Power Engineering International on Twitter

Related Articles

Kuwait approves $9.9bn power infrastructure plan

$9.9bn is to be spent in improving Kuwait’s power generation capacity to help it meet the increasing demands.

Largest Jenbacher order for GE at German gas-fired plant

A power plant at Kiel in Germany is to take a delivery of 20 Jenbacher J920 Flextra gas engines with a power output of 190 MW, which represents the largest sale in the history of the Jenbacher company, according to GE.

Latest Articles

Editor's Picks

GE unveils transformational Digital Power Plant

GE yesterday unveiled a digital initiative that it claims will revolutionise the power industry and save plant operators b...
Anne Carpenter of IEA Clean Coal Centre

Report highlights need for enlightened approach to water and power generation

The International Energy Agency’s Clean Coal Centre has produced its latest insights into what is referred to as the ‘wate...

UK gives £2bn backing to Hinkley Point nuclear project

The UK government has reaffirmed its commitment to Hinkley Point C new nuclear power station by unveiling a £2bn ($3.1bn) ...

Policy tinkering sees financial lure of UK renewables sector plummet

The UK’s attractiveness for renewables investment has plummeted in the last few months thanks to “policy-making in a vacuu...

US leapfrogs China to top renewables investment table

The US has leapfrogged China to the top slot in a highly-regarded annual analysis of the best countries in the world for r...

Editorial Guides

Lubrication Challenges for the Biogas Industry in 2015

The biogas industry is growing in importance as the world continues to look for alternative, clean energy sources. However...

Maximising Power Plant Efficiency

The need for power plants to operate at maximum efficiency and flexibility while cutting emissions is greater than ever be...

How to cut your OPEX

How to cut your OPEX In a constantly evolving electricity market, factors such as over capacity and low coal costs can pu...

Buyers Guide Companies

Rolls Royce Energy Systems

We supply gas turbines, compressors and diesel power units to customers ...

Bran & Luebbe, An SPX Brand

Bran & Luebbe, an SPX brand, has been a worldwide leader in metering, an...

Lenox Instrument Co

Lenox Instrument Co is a manufacturer of highly reliable fixed and porta...

ATG Electronics

For more than a decade, ATG Electronics has established itself as a lead...

SWAN Analytical Instruments AG

Is one of the leading manufacturers of online analytical instruments.

Buyers Guide Products

Excitation System

Our excitation systems are recognized worl...


Compact voltage regulator, integrates all ...

MHT410 Moisture, Hydrogen and Temperature Transmitter

The Vaisala Moisture, Hydrogen and Tempera...

DMT340 Series Dewpoint and Temperature Transmitters for Very Dry Conditions

The Vaisala DRYCAP® Dewpoint and Temperatu...

Control Servo Motor SMR

A Voith control servo motor is a linear el...

Power Engineering International


The Effect of Moisture Sensor Location on Reliable Transformer Oil Monitoring

Power transformers are among the most valuable and important assets in electrical power networks and moisture is one of the key factors impacting the operational performance of transformer oil.&nbs...

Engineering & Design for Lean Construction

AVEVA introduces the benefits of Engineering and Design for Lean Construction by challenging the concept of ‘right first time design' and presenting a ‘Lean’ approach. A Lean approach to project ex...

Bridging the Power Gap in Africa: Testing options to manage constrained short to medium term system operations

Around the world, existing power systems face increasingly constrained operations in the short to medium term with available ageing generation capacity.  In this paper, PLEXOS® has been used t...

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New challenges and opportunities are continually appearing thanks to dramatic developments in technology...

Latest Digital Edition

Look Inside >
Current Issue

Article Archives for Power Engineering International Magazine