Indonesian state-owned utility Perusahaan Listrik Negara (PLN) formally launched operations at three new coal-fired power plants.
The 625 MW Banten 1 plant in Suralaya, Banten, a $478m project built by the China National Technical Import and Export Corp. and Indonesia’s state-owned Rekayasa Industri, is expected to consume 2.9 million metric tons of coal annually, with supplies coming from Kalimantan and Sumatra on a 20-year contract.
The $808.4m Banten 3 project in Lontar, Banten, has a capacity of 3 x 315 MW and was built by a consortium that included Chinese power equipment giant Dongfang Electric Corp. and Dalle Energy.
The two Banten plants are expected to be supported by the completion of a transmission network connecting Labuan, Saketi, and Rangkas Bitung, three cities in Banten province.
In central Java, the government also started up two new 662-MW units at the existing 1320 MW Tanjung Jati B coal fired power plant.