21 August 2002 - Work has begun on a 500 kV transmission line that will carry power to Ho Chi Minh City and the southern provinces of Vietnam. The VND 1506bn ($100m) Electricity Corporation of Vietnam [EVN] project, which will link the Phu My power plant, in Ba Ria-Vung Tau Province, with Ho Chi Minh City, is expected to be completed by the end of next year.

It will run across Ba Ria-Vung Tau and Dong Nai provinces and Ho Chi Minh City. The project, besides the transmission line, will include the construction of Nha Be and Phu My sub-stations, and the expansion of Phu Lam Sub-station.

"The 500kV transmission line is very important and construction must be completed quickly. The line will connect the Phu My No. 3, Phu My No.2 and Phu My No. 4 plants with the national grid," said general director of EVN, Dao Van Hung.

Their combined output will be 1900 MW while the Phu My Complex is totally expected to generate 3875 MW by mid-2004. The project will be financed by official development assistance loans from the Japan Bank for International Co-operation and EVN's own resources.

"The 500 kV line will not only pave the way for the socio-economic development of Ho Chi Minh City but also the rest of the country. It will also help attract foreign investment to the region," said Hiroshi Suzuki, chief representative of JBIC in Vietnam.

"I hope the contracts for supply of materials and sub-stations will be completed soon, and construction work carried out smoothly, so that the 500kV line will be in operation by mid-2004."

EVN general director Hung added that demand for power has been increasing sharply and EVN aims to construct more than 4000km of 500 kV transmission lines soon.

Recommend this article Recommend this article () Yo recommended this article Yo recommended this article ()
Follow Power Engineering International on Twitter

Editor's Picks

Borwind

Siemens to lead major grid connection project

Siemens has been chosen to lead a consortium responsible for constructing and installing an offshore wind connection in th...
Rajendra Pachauri

UN advocates tripling of renewables and nuclear energy

A report from the United Nations Intergovernmental Panel on Climate Change (IPCC) has warned that the world needs to drast...
Temelin NPP

$15bn Czech nuclear power project cancelled

The president of the Czech Republic, Milos Zeman, has called for a $15bn tender designated for the expansion of the countr...
Dr Joachim Hein

Brussels and Berlin actions on renewables welcomed by German business lobby

The Association of German Industry, or Bundesverband der Deutschen Industrie (BDE), has expressed relief at the news that ...
Maria van der Hoeven

IEA praises Austria for ‘balanced’ energy policy

The International Energy Agency focused on Austria for its 2014 country review, launched on Wednesday, and while fulsome i...

PEI Magazine Issues



>> Current Issue           >> Past Issues

Latest Wire News

Artesyn Embedded Technologies Announces First Titanium Efficiency Front End Power Supply

Artesyn Embedded Technologies Announces First Titanium Efficiency Front End Power Supply

Intergraph(R) Webinar on April 24th to Demonstrate CADWorx(R) E&I Automation of Project Documentation for Electrical and Instrumentation

Intergraph(R) Webinar on April 24th to Demonstrate CADWorx(R) E&I Automation of Project Docu...

Woodward Reports Second Quarter and Six-Month Fiscal Year 2014 Results

Woodward Reports Second Quarter and Six-Month Fiscal Year 2014 Results

Covanta Holding Corporation Reports 2014 First Quarter Results and Affirms 2014 Guidance

Covanta Holding Corporation Reports 2014 First Quarter Results and Affirms 2014 Guidance

Energy Sector Demand Strong for Traditional Satellite Capacity

Energy Sector Demand Strong for Traditional Satellite Capacity

Editorial Guides

How to cut your OPEX

How to cut your OPEX In a constantly evolving electricity market, factors such as over capacity and low coal costs can pu...

Alstom Editorial Guide: Thailand to showcase latest upgrade of Alstom's GT26 in combined-cycle

Read all about Alstom's new advanced GT26 gas turbine in the North Bangkok CCPP expansion project online with the Power En...

PLEXOS® Integrated Energy Model – Leading the Field in Energy Market Modelling

PLEXOS® Integrated Energy Modelling is an advanced software tool that employs the latest mathematical programming methods ...

Power Engineering International

Whitepapers

Evaluating cogeneration for your facility: A look at the potential energy-efficiency, economic and environmental benefits

The energy-efficiency, economic and environmental benefits of cogeneration are the subject of this in-depth white paper. The paper argues that producing electricity and heat/cooling from the same f...

The Effect of Moisture on the Breakdown Voltage of Transformer Oil

Power transformers utilize oil as a heat transfer medium and a dielectric material, together with cellulose. Breakdown voltage (dielectric strength) is one of the most important parameters of trans...

Improving Mission Critical Cooling Systems With More Reliable Level Sensing

The choice of coolant level sensor may seem like an insignificant detail when designing complex machinery such as emergency generators and cranes, but if this sensor fails, the operator has no warn...

Steps Towards a Low Carbon Future: Solutions and Technologies That Will Support the Global Revolution Required

A smart grid is becoming more and more essential as clean energy becomes more dominant. In addition, the demand for electricity is expected to treble the ability to supply it over the next decade. ...

Latest Digital Edition

  Power
  Engineering
  International
Look Inside >
Cover
Current Issue

Article Archives for Power Engineering International Magazine

Latest Energy Jobs